(solved)Question 3 SSC-CGL 2018 June 4 Shift 2

The ratio of competencies A, B and C is 4: 5: 3. On working together, all three of them complete work in 25 days. In how many days will both A and C together complete 35% of the work?
(Rev. 05-May-2025)

Categories | About Hoven's Blog

Parveen,

Question 3
SSC-CGL 2018 June 4 Shift 2

The ratio of competencies A, B and C is 4: 5: 3. On working together, all three of them complete work in 25 days. In how many days will both A and C together complete 35% of the work?

  1. 18
  2. 15
  3. 12
  4. 10

Solution 1

Work that A+B+C can together do in 1 day is 4k+5k+3k=12k\displaystyle 4k + 5k + 3k = 12k.

Total work in 25 days = 25×12k=300k\displaystyle 25 \times 12k = 300k

Days taken by A+C to complete (4k + 3k) = 7k work is = 1 day

\displaystyle \therefore days to complete 35%×300k\displaystyle 35\% \times 300k will be 17k×35%×300k=15\displaystyle \frac{1}{7k} \times 35\% \times 300k = 15 days Ans.

EXPLANATION: efficiency means "the amount of work done in 1 day". Ratios are given so we should say that A completes 4k work in one day, B completes 5k, and likewise C completes 3k work. They together complete (4k + 5k + 3k) work in a day. On the same lines, we can conclude that A and C together complete (4k + 3k) amount of work in a day.

Solution 2

This is the classic, school math approach.

Total units of work are 25\displaystyle 25

A + C can complete 4+34+5+3=712\displaystyle \frac{4 + 3}{4 + 5 + 3} = \frac{7}{12} work in 1 day

Work to be done by A and C is 35%×25\displaystyle 35 \% \times 25 units

Hence, they complete this work in 17/12×35%×25=15\displaystyle \frac{1}{7/12} \times 35 \% \times 25 = 15 days Ans.

Solution 3

Use the principle that M×DW\displaystyle \frac{M \times D}{W} is constant. M = number of men, D = days they work, and W is the fraction, or amount of work they do.

When A+B+C work together, M1=4k+5k+3k=12k\displaystyle M_1 = 4k + 5k + 3k = 12k, D1=25,W1=1\displaystyle D_1 = 25, W_1 = 1

When A+C work together, M2=4k+3k=7k\displaystyle M_2 = 4k + 3k = 7k, D2=x,W2=0.35\displaystyle D_2 = x, W_2 = 0.35

Now, M1×D1W1=M2×D2W2\displaystyle \frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2}

Hence, 12k×251=7k×x0.35\displaystyle \frac{12k \times 25 }{1} = \frac{7k \times x}{0.35}

Solving, x=15\displaystyle x = 15 days, Ans.

Creative Commons License
This Blog Post/Article "(solved)Question 3 SSC-CGL 2018 June 4 Shift 2" by Parveen is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.